Jul 06, 2018

The Rise Condos - Grand Opening Event & July Construction Update

Summer is in full swing and so is the construction progress at The Rise Condos. Our builders are working tirelessly in the hot summer sun towards our first target possessions for Winter 2018.  

We are also excited to announce a Grand Opening event for The Rise Condominiums' new Display Suite and Presentation Centre located at 300 Centre Street in Bridgwater Centre. The event will be from 3-7pm on Tuesday, July 31st and will include a live show by Grant Leutschaft, a live on location with QX 104 FM, tasty food & beverages and much more. Plus you'll be among the first in Winnipeg to tour the new display suite.  

                        Click here to visit our event page and to RSVP  


grand-opening-event-rise

If you're one of our many excited purchasers at The Rise, read on to see all of the work that has been completed or is underway as of late!

 

Parkade

  • All concrete work completed
  • Electrical rough in completed
  • Plumbing rough in completed
  • Sprinkler rough in completed
  • Masonry walls 90% completed

 

1st Floor

  • All concrete work completed
  • Interior steel stud framing completed
  • Exterior steel stud framing completed
  • Exterior sheathing installed
  • Window install completed
  • Patio door completed
  • Electrical rough in completed
  • Plumbing rough in well under way
  • Display suites are boarded, taped, painted, floors are in and cabinets installed

 

2nd Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Interior walls completed
  • Windows installed
  • Plumbing rough in underway
  • Electrical rough in underway
  • HVAC rough in completed

 

3rd Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Windows installed
  • Interior walls completed
  • Plumbing rough in underway
  • Sprinkler rough in underway
  • HVAC rough in completed

 

4th Floor

  • Insulation/vapor barrier install underway
  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Windows installed
  • Interior walls completed
  • Electrical rough in completed
  • Plumbing rough in underway
  • HVAC rough in completed

 

5th Floor

  • Drywall complete
  • Drywall taping underway
  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Windows installed
  • Interior walls completed
  • Plumbing rough in underway
  • Electrical rough in underway
  • HVAC rough in underway
  • -Bulkhead framing started

 

6th Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Windows installed
  • Interior walls completed
  • Plumbing rough in completed
  • Electrical rough in completed
  • HVAC rough in completed
  • Bulkhead framing completed
  • Drywall taping complete
  • Drywall complete

 

7th Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Ceilings are all dry walled
  • Interior walls completed
  • Plumbing rough in completed
  • HVAC rough in completed
  • Electrical rough in completed
  • Sprinkler rough in completed
  • Drywall complete
  • Drywall taping complete
  • Suite priming complete
  • -Gypcrete topping complete

Exterior

  • Building commercial wrap installation completed
  • Building water membrane install completed
  • Patio doors and windows are installed
  • Main roof install 100%
  • East and west elevation brick and tyndall stone completed
  • EIFS systems underway